Guides
Lead times by brand, our conditions and successors of discontinued series at a glance.
Lead time index
Most common lead time by brand according to our purchasing system, as of 05/11/2026. Lead times are estimates. The quote is binding.
| Brand | Stock items | Production items |
|---|---|---|
| Siemens | 10 to 15 working days | |
| ABB | 10 to 15 working days | 6 to 8 weeks |
| Schneider Electric | 10 to 15 working days | 6 to 8 weeks |
| Phoenix Contact | 10 to 15 working days | 6 to 8 weeks |
| Eaton | 8 to 9 working days | 5 to 7 weeks |
| Murrelektronik | no stock offers | 5 to 7 weeks |
| Omron | no stock offers | 6 to 7 weeks |
| Sick | no stock offers | 5 to 7 weeks |
| Turck | no stock offers | 5 to 7 weeks |
| Schmersal | no stock offers | 5 to 7 weeks |
| Pilz | no stock offers | 5 to 7 weeks |
Conditions
- New, factory sealed
- New items in the manufacturer's sealed packaging. Factory sealed items keep the manufacturer warranty.
- New surplus
- Unused new items from surplus stock, possibly without original packaging. The warranty is stated in the quotation.
- New
- Production items from the manufacturer's current production, lead time in weeks.
No used items. We state the condition in every quotation.
Successors of discontinued series
| Series | Brand | Status | Successor |
|---|---|---|---|
| SACE New Emax | ABB | phase-out | SACE Emax 2 |
| SACE Tmax T | ABB | phase-out | SACE Tmax XT |
| SIMATIC ET 200S | Siemens | discontinued | SIMATIC ET 200SP |
| SIMATIC S7-1200 | Siemens | phase-out | SIMATIC S7-1200 G2 |
| SIMATIC S7-300 | Siemens | discontinued | SIMATIC S7-1500 |